AI, Energy and Climate

Laurenceo IntelligenceUpdated 21 November 2026
Cooling plant on a data centre roof
Cooling plant on a data centre roof. Image credits

Laurenceo Intelligence tracks the energy cost of AI: data centre power demand, grid connections, nuclear and renewable deals, and the climate and resilience questions they raise.

  • 18 developments
  • 7 organisations
  • 4 live forecasts
  • Updated 21 November 2026
  • Tracked since 28 September 2026
Desk briefing · 21 November 2026

Grid access, not chips, now decides where AI capacity gets built

Power contracts, grid connection dates and local consent are setting the pace of AI infrastructure. The newest evidence is a Harvard estimate of US hyperscale power use 1 and Microsoft's exit from a UK site over a grid delay 7.

The Picture Now

Academic estimates put US hyperscale data centre electricity use at 68 to 99 TWh, with the upper figure approaching annual consumption in states such as Indiana, Michigan and Tennessee 1. Power is being locked up on long terms, with Google contracting 3,590MW from Constellation in PJM under 15- and 20-year agreements 14. PJM expects peak load to grow by up to 30GW through 2030, largely because of AI data centres 14.

Connection dates and local consent now decide capacity as much as capital does. Microsoft ended its anchor tenancy at Nscale's Loughton site after reports that sufficient power would not arrive until the early to mid 2030s 67. Opposition is also hardening, with AWS's chief executive warning that more than 100 data centre moratoriums are under consideration in the US 16, and a Virginia bill proposing a three-year pause on approvals 11.

What Changed Recently

ReNew announced a 1 GW renewable-powered hyperscale data centre in Anakapalli, Andhra Pradesh, within a package of about INR 80,000 crore 2. Google's US$15 billion Malaysia plan arrived as DC Byte data put Malaysia at more than half of the Southeast Asian capacity under construction, and the report notes pressure from communities and regulators 3. Alliant Energy expects to sign about 1 GW of additional data-centre contracts within six months and raised its 2027 to 2030 capital plan by 19% 4.

In October, FERC approved a PJM registry recording data centre load ramps and backup generation, but rejected a plan to curtail grid power to data centres at peak 12. Anthropic signed a lease at EverWind's Point Tupper campus in Nova Scotia, where the initial 95 MW facility is due online in late 2027 910. Amazon, AEP and X-energy agreed to explore 960 MW of small modular reactors in Indiana, but no final investment decision has been taken 8.

What It Means

Power access has become the binding constraint and the main point of differentiation. Hyperscalers that can sign multi-decade energy contracts will secure capacity ahead of smaller providers, and those terms will feed into cloud pricing and regional availability 1415. Microsoft kept its US$30 billion UK investment plan while exiting one site, which shows that a headline investment figure does not guarantee usable megawatts 5.

The cost of the grid build-out is shifting towards the companies building the compute. EverWind says it will fund electricity infrastructure so costs are not passed to ratepayers 10, and AWS has committed to cover utility upgrade costs so residents' bills do not rise 16. Amazon's role as both early funder and long-term offtaker of the Indiana reactor plan moves development risk away from the utility 8. Enterprises should treat regional power availability as a limit on capacity and price.

What to Watch

  • Whether Alliant Energy signs the roughly 1 GW of additional data-centre load it expects within six months 4. The forecast probability of signed contracts by 30 April 2027 is 52 per cent.
  • Whether Virginia's Senate Bill 843 advances, since a three-year pause from 1 July 2027 would reshape approval timing for the state's capacity 11.
  • Whether Gorilla Technology completes its letter-of-intent acquisition by the end of November 2026, which would test its 36 MW utility-backed route 13.

Numbered links open the sourced story behind each point.

Lead Development

21 November 2026

Harvard study estimates US hyperscale data centres used 68 to 99 TWh of electricity

Researchers estimated energy use and carbon emissions for hyperscale data centres. Depending on how hard the facilities were running, they together used between 68 and 99 terawatt-hours of electricity, with the upper estimate approaching annual use in states such as Indiana, Michigan and Tennessee. Emissions were attributed to each facility using EPA data on the power plant mix in its regional grid.

Why it matters. Facility-level estimates that compare data centre demand with whole-state consumption give utilities, regulators and local opponents a concrete reference for grid planning and permitting disputes. Hyperscalers and AI infrastructure developers are exposed to tougher scrutiny of siting, power sourcing and emissions claims. Corporate sustainability teams should expect independent academic figures to be set against their own disclosures.

Read the full story →

This Week

Earlier Coverage

Forecasts

Open questions on the Laurenceo forecast board, with the current probability.

Organisations

Every Desk

Next deskFrontier AI Models →Latest: Gottheimer and Moran introduce bill requiring reporting on automated AI research and development

Laurenceo Intelligence is the daily AI intelligence briefing published in Bermuda by Laurenceo and edited by Jorai Laurenceo. Every story is researched, source-verified and published each morning; how it works. General information only, not legal, regulatory or financial advice.